Next Steps:

June 2021

Further 2021 consultation with feedback considered.

March 2022

Planning application submitted to Camden Council

Mid-late 2022

Expected planning decision from Camden Council.

2023

Construction works to commence, subject to planning permission, beginning with enabling works for Crossrail 2.

2026

Once enabling works on Crossrail 2 are completed, construction on the British Library extension will commence.

2029

Expected completion date for the works and opening.